BC’s Power Generation Struggles Amid Rising Demand for Renewable Hydropower

Summary

  • A delay in the expansion of a northern transmission line means that LNG plants will be operational years before the expansion is ready, due to extended regulatory processes.
  • British Columbia increased its electricity grid expenditure by 50% on Tuesday as industry demand for renewable hydropower grows and the province shifts to electric vehicles and electric heating.
  • Providing hydropower to LNG initiatives, including LNG Canada, is integral for the province and Canada to drastically reduce emissions by 2030.
  • LNG Canada, which is 90% complete, will function using high-emission natural gas, posing a challenge to Canada’s net-zero targets.

Challenges in the Face of Increased Demand

As Barry Penner, former B.C. environment minister and current chair of Energy Futures Initiative stated, satisfying the growing demand for electricity is a significant challenge. The expansion of a northern transmission line, essential for the operations of LNG plants, will not be ready until years after these plants commence work.

Impact on Net-Zero Goals

Running LNG Canada and other similar projects on high-emission natural gas complicates the ambitions of the province and Canada as a whole to drastically cut emissions by 2030. The delay in the expansion project for the electricity grid is likely to impact these goals.

Importance of Swifter Electricity Expansion

The message from industry, particularly LNG Canada, is one of encouragement for governmental actions to accelerate the expansion efforts. B.C.’s electricity grid plans to expand critical northwest transmission lines, with an estimated cost of around C$3 billion. The expansion is scheduled to take up to a decade, allowing for necessary agreements with First Nations and permit acquisition.

First Nation’s Support

Strong support from First Nations could potentially fast-track the regulatory timeline, with K’uul Power, a consortium of 11 First Nations, currently in discussions to purchase 50% of the project from BC Hydro.

Hydropower and LNG Industry

Similar to Quebec, B.C. draws most of its power from hydro. Coupled with its coastal ports, this gives the province a key role in Canada’s budding LNG industry. However, B.C. faces challenges such as frequent droughts, which cut down hydropower generation.

Risks and Prioritization

However, it remains questionable if B.C. will be able to generate enough power to meet the requirements of all industries, including those like LNG and mining of critical minerals. As Evan Pivnick, program manager at Clean Energy Canada, questions, “which industries is it prioritising?”

Pertaining to the trading landscape, these developments are likely to impact the energy trading dynamics and put a spotlight on alternative power-focused assets.

($1 = 1.3511 Canadian dollars)